Field/Option | Description |
Import Project
|
Click to import (or re-import) the selected project. If the project contains scenarios, you will first need to remove the scenarios before importing the project.
|
Import Cost Data
|
Click to use the Cost Data Import Wizard to import cost data from Deltek Cobra, a Work Authorization Document (WAD), or a .csv file. This option is only enabled if the
Deltek Cobra / Cost Data and WAD option on the Platforms (Deltek) page of the Deltek Acumen Options dialog box is selected.
|
Lock Content
|
Click this command to lock the project so that the data cannot be overwritten. This feature is useful if you want to keep and compare historical data. When a project is locked, you cannot use
Import All for the selected project. You can still use
Import in which case Acumen will add a new project snapshot.
|
Filter
|
Click to add filters to the project data. Clicking this command displays a sub-menu where you can select filtering options before you import the data. You can also filter the data using the
command.
|
New Snapshot
|
Click to add a new snapshot of the project. A snapshot allows comparisons between versions of a single project. Clicking this command displays a sub-menu where you can select the type of snapshot you want to add.
|
Delete
|
Click to delete the selected project from the workbook.
|
Assign Baseline
|
Click to assign a baseline to a P6 schedule. Assigning a baseline allows you to compare baseline data with the current schedule. This command is only available for Primavera P6 projects.
|
Assign Baseline and add Snapshot
|
Click to assign a baseline to a P6 schedule
and add a snapshot. This command is only available for Primavera P6 projects.
|
Clear Baseline
|
Click to clear the P6 baseline. This command is only available for Primavera P6 projects that have a baseline.
|
Merge with Excel File
|
Click to merge the selected project with an Excel file. After you select the Excel file, an Excel Merge dialog box displays where you can select the workbook and ID column.
|
Set Text Encoding
|
Click to set text encoding for a Primavera XER project.
XER files do not include any information about what is being used to encode the files. If the file does not use standard encoding (for example, it uses Russian instead of English), then the characters may not display correctly when you import the file.
Set the text encoding after you have linked the Oracle Primavera project but
before you import the data.
|
Create Scenario
|
Click to create a scenario for the selected project. Scenarios are very similar to snapshots and are schedules created directly within Acumen. You can use them to compare to their respective parent projects using the Forensic Analyzer and Analysis views.
|
Export as UN/CEFACT
|
Click to export the selected project as a UN/CEFACT file. This command is not available for all project types.
|
Export as Microsoft Project XML
|
Click to export the selected project as an MSP .XML file. This command is not available for all project types.
|
Export as Oracle Primavera P6 XER
|
Click to export the selected project as an Oracle Primavera P6 XER file. This command is not available for all project types.
|
Export to Deltek Open Plan
|
Click to export the selected project to Deltek Open Plan. This command is not available for all project types.
|